ISO 9001 CNC Supplier Checklist: 10 Questions Before an RFQ

ISO 9001 CNC Supplier Checklist: 10 Questions Before an RFQ

Which ten questions help qualify a CNC quotation?

Use the checklist to identify evidence and unresolved requirements before quotation or trial release. A yes/no answer should lead to a document, process explanation or agreed next step rather than a general marketing claim.

Checklist result Purchasing action before release
Answer supported by evidence Record the document, revision, scope and person responsible for acceptance.
Answer depends on the component Send the controlled drawing and request a specific feasibility response.
Exception or missing evidence Keep the requirement open and assign an owner and resolution deadline.
Trial proposed Agree the quantity, inspection package and approval needed before repeat supply.

Attach the completed checklist to the RFQ review. A total score or a row of yes answers should not override an unresolved requirement that is essential to your component.

published TDB certificate documents. RFQ checklist.

Supplier identity

1. Which legal company and manufacturing site will fulfill the order? 2. Can required certification be independently verified?

Match the quotation, invoice and manufacturing site to the organization being qualified. Where a trading business coordinates another factory, record that relationship and who accepts responsibility for the delivered parts. Compare any certificate with the actual legal entity, site, scope and dates. Use the issuing body’s current status information where available; a certificate image alone may not answer those questions. ISO explains that external certification bodies perform certification. Keep certification review separate from the part-specific technical assessment.

Technical and production scope

3. Which drawing revision is being quoted? 4. Is the specified material and condition available? 5. Which operations will be subcontracted?

Provide a controlled file register, drawing/model references, units and approved revision. Ask the supplier to list conflicts or missing requirements before pricing. For material, confirm the exact grade, product form, condition and required records, with a dated availability assumption. A familiar alloy name does not authorize substitution. Identify external finishing, heat treatment or specialist inspection and agree who transmits the specification, retains lot identity and checks returned work. Record any buyer approval needed before changing the source or route.

Quality evidence

6. How will critical features be inspected? 7. Which material and lot records will accompany supply? 8. What initial-part evidence is required?

Select representative functional characteristics from the drawing and ask for the proposed measurement method, datum setup, process stage and reporting coverage. Owning an instrument does not prove that every feature can be verified. Agree how results identify the part, revision, sample or lot, and how material evidence connects to the stock actually used. Define what the first-part or trial submission must demonstrate and who accepts it. A passing prototype should not silently authorize a larger production quantity or a changed manufacturing process.

Commercial and release scope

9. Which tooling, finishing, packaging and delivery items are included? 10. Who approves the part and any later changes?

Mark each deliverable as included, excluded or unresolved. Separate programming, setup and dedicated tooling from recurring unit prices where relevant. Confirm the delivered finish, protection, inspection records, quantity and delivery milestone. A blank price line should not be read as an included service. Name the technical and commercial decision owners, record approved deviations and define how revisions affect work in progress or stock. Close essential gaps before release and retain the accepted quotation and acknowledgement with the completed checklist.

Does a completed checklist automatically approve the supplier?

No. Resolve the answers against the buyer’s approval process. Review the required evidence and trial results before releasing production or allocating recurring demand.

Request a project-specific review

Send the controlled drawing, material, quantity and required evidence through the contact TDB Hanoi page. Confirm the agreed scope in the quotation before releasing work.

Certificate evidence for TDB Hanoi

For TDB Hanoi’s published certificate details, company and production-site scope, original documents and the issuing body’s lookup link, see our ISO 9001:2015 certification evidence. The evidence page shows the certificate dates; continue to check the issuing body’s current status during supplier approval.